Customer Support: 866-526-9266
        

Wed. May 15, 2024
12:50 AM UTC
     
 

Marketplace Login
Please place this page in your favorites area as this
is the login page to access the software.

If you are prompted by your computer to save your
password, for security reasons choose "No."

 
E-mail  
 
Password  
 
Forgot Password?
Not registered? Sign-up Now as a Vendor
 
 
 



 
 Contact  Customer Support: 866-526-9266 © Copyright 2024, International eProcurement   
Housing Agency Marketplace - Housing Agency Marketplace
 
Customer Support: 866-526-9266
        

Wed. May 15, 2024
12:50 AM UTC
     
 

Agency Lucas Metropolitan Housing Authority Request # 15-B008
Buyer Name Erin Traynum-Cameron
(etraynumcameron@lucasmha.org)
Buyer Phone #
Main Service/Commodity Category Construction, Maintenance, Support and Repair Services
Request Title Interior Renovations to Three Units at Olander Estates Due Date 12/08/2015
Contract (Award) Option: Due Time 04:00 PM UTC
 
Date: 11/25/2015 11:31 AM UTC
Title: Specification clarification
Question(s) and Comment(s): The specifications for the 1/2 bathroom and the full bathroom call for "Vanity cabinet to be Certified HUD Severe Use Cabinet", could you provide a copy of this guideline?

The plumbing section of the specification only discusses the installation of new gas piping. With the installation of new vanities in the 1/2 bathroom, full bathroom and new sink going in the kitchen, are we expected to provide new water supply lines and drain lines. Or should we use existing assuming the lengths work? This also pertains to the new toilet and its supply lines, and will assume soil pipe flange is in good working condition and will not need adapter or repaired.

The plumbing section of the specification does not discuss shut-off valves, Contractor will assume they all hold for kitchen sink, 1/2 bathroom vanity and toilet, full bathroom and toilet, utility sink. Contractor also assumes main water shut-off is in good working condition should any of these valves fail.

Contractor assumes main water shut-off is in good working condition to isolate water to full bathroom for the removal of shower fixtures and installation of new. Specification also does not mention the installation of shut-off valves at the shower hot/cold water supply lines to isolate the shower faucet should future issues occur, please confirm.

Electrical specification calls for the baseboard heater removal of "...wiring that feeds into box shall be removed as much as feasibly possible without the removing of drywall...", installing caps/electrical tape and abandon in walls please confirm.

Will this project be on a "Progress Payment Schedule" to include payment requests for mobilization, 20% complete, 40% complete, 60% complete, 80% complete then the final billing that will include retainage; please confirm this or offer an alternate plan.